Both offshore pipelines will start near Anapa, on the Russian coast, and land on the Turkish coast near Kiyikoy, at a distance of 100 kilometres to Istanbul. Of the two onshore pipelines, BOTAS will develop the first line in Turkey, which will connect to the Turkish network at Lüleburgaz. The second onshore line, which will run towards the Greek-Turkish border, will be realized jointly by Gazprom and BOTAS.Constructing the Offshore Pipeline
When complete each line will be capable of delivering 15.75 billion cubic metres of gas per year. A single line will be constructed from thousands of individual pipe joints. Each of these pipe joints has an external diameter of about 81 cm and weighs around 9 tonnes. The walls of the pipeline are made up of almost four centimetres of high-quality carbon manganese steel. Pipes laid closer to the shore are coated in concrete for added stability and protection against marine activities.
The pipes are welded together on board specialized pipelaying vessels. Each weld is scanned with ultra-sound, which can help detect even the tiniest defects in the welding joint. After the joints are coated for protection against corrosion, the vessel moves forward and the pipe is lowered onto the seabed.
31.5 bcm capacity, 15.75 bcm per line
2 lines, each over 900 km in length
Laid at depths of 2,200 metres
12 metre pipe-joints make up each pipeline● 81 cm external diameter● 9 tonnes weight● 4 cm wall thickness Over 75,000 pipes used per line
300 bar internal design pressure
284 bar maximum operating pressure
TurkStream will supply energy equivalent to: