TurkAkim 2 will pass through the straits for the pipeline

TAKİP ET

The world's largest construction ship, Pioneering Spirit, will cross the Bosphorus for the third time at 06:00 in the morning to make the TurkAkim Natural Gas Pipeline in the Black Sea.

The world's largest construction ship, Pioneering Spirit, will cross the Bosphorus for the third time at 06:00 in the morning to make the TurkAkim Natural Gas Pipeline in the Black Sea.

After Pioneering Spirit crossed the Bosphorus and opened to the Black Sea, TurkAkim will continue to build the second line, which has already completed 224 kilometers, and will reach the Kıyıköy.

The TurkStream Gas Pipeline
TurkStream will directly connect the large gas reserves in Russia to the Turkish gas
transportation network, to provide reliable energy supplies for Turkey, South and Southeast
Europe. The offshore component of TurkStream Pipeline will be developed and constructed
by South Stream Transport B.V., a 100% subsidiary of Gazprom based in Amsterdam,
The Netherlands. The offshore pipeline will consist of two parallel pipelines running through
the Black Sea.


Both offshore pipelines will start near Anapa, on the Russian coast, and land on the Turkish
coast near Kiyikoy, at a distance of 100 kilometres to Istanbul. Of the two onshore pipelines,
BOTAS will develop the first line in Turkey, which will connect to the Turkish network at
Lüleburgaz. The second onshore line, which will run towards the Greek-Turkish
border, will be realized jointly by Gazprom and BOTAS. Constructing the Offshore Pipeline

Constructing the Offshore Pipeline
When complete each line will be capable of delivering 15.75 billion cubic metres of gas
per year. A single line will be constructed from thousands of individual pipe joints. Each
of these pipe joints has an external diameter of about 81 cm and weighs around 9 tonnes.
The walls of the pipeline are made up of almost four centimetres of high-quality carbon
manganese steel. Pipes laid closer to the shore are coated in concrete for added stability and protection against marine activities. The pipes are welded together on board specialized
pipelaying vessels. Each weld is scanned with ultra-sound, which can help detect even the tiniest defects in the welding joint. After the joints are coated for protection against corrosion, the vessel moves forward and the pipe is lowered onto the seabed.

The TurkStream Offshore Pipeline in Numbers

31.5 bcm capacity, 15.75 bcm per line
2 lines, each over 900 km in length
Laid at depths of 2,200 metres
12 metre pipe-joints make up each pipeline
● 81 cm external diameter
● 9 tonnes weight
● 4 cm wall thickness
Over 75,000 pipes used per line
300 bar internal design pressure
284 bar maximum operating pressure
TurkStream will supply energy equivalent to:
● The energy consumed by 19 million European households
● The power capacity of nearly 25,000 wind turbines
● The amount of gas delivered by almost 350 LNG tankers

(ee).

pioneering spirit turkakim