With the commissioning of the power plant the increasing energy consumption needs of Tunisia are planned to be met.

The 450 MW Rades-C Power Plant in Tunisia, in which GAMA Power Systems was involved in the construction, is in the process of a 4 month “Industrial Commissioning”. The electromechanical installation works are ongoing and construction works of our project have been completed to a large extent. With the commissioning of the power plant the increasing energy consumption needs of Tunisia are planned to be met.