Following the successful completion of the Hartha Unit-4 Thermal Power Station Rehabilitation as GAMA Power Systems, the construction works of 200MW Hartha Unit-1 Thermal PowerStation hashtag Rehabilitation started on October1, 2019. The contract was signed on November 19, 2017 as GAMA Power Systems and Mitsubishi Hitachi Power Systems with the Iraqi Ministry of Electricity and the Basra General Directorate of Electricity & Power Generation. Mobilization works of the project have been completed and electromechanical activities are continuing rapidly with more than 300 employees. The progress of the project has reached 19.37%, and is planned to be completed in November 2020.